Friday, September 2, 2011

Lenny Hoffman Excavating is completing the underground work for the Hunter Road reconstruction project. All water main and sanitary sewer work is complete and by Friday all underground work will be finished.

Curb preparation and installation work on the west side of Hunter Road will commence on Tuesday morning, September 6th, and will be completed by Monday afternoon, September 12th. Driveway access to these homes will be restored beginning Tuesday morning, September 13th.

All cars parked at residences in the areas listed above will not have access to driveways after 7:00 AM on Monday morning and should park on Indian Road or Wilmette Avenue. No cars should be parked on Hunter Road between 7:00 AM and 6:00 PM. Please plan accordingly.

After the west side driveway accesses have been restored, the east side of Hunter will be completed and you will receive notification for this. After the concrete work is complete, paving of the new road will begin, depending on the weather conditions. We will keep you posted as to the schedule.

Thank you for your patience during this project. Feel free to contact the Capital Projects Department at (847) 998-9500 if you have any questions or concerns.